WHR
Archive News 2001/2
V4.1 dated 29/12/04
Tamper squad formed
The WHLR has set up a four-man tamper squad to work on the trackbed alignment and tamping using the new tamper. The first task is to get the vertical levels correct. Finally, the horizontal alignment will be set using appropriate transition curves. The tamper has been fitted with tines suitable for steel sleepers rather than concrete as originally fitted.
A ballast regulator is under construction in the machine shop at Dinas on temporary rails. This will be fully fitted with hydraulic mechanisms. The regulator will be dragged uphill by Upnor Castle. The aim is to have Upnor Castle, a single ballast wagon and the regulator moved on a lorry to isolated sections such as Rhyd Ddu to Glan-yr-afon and to work that section and make it suitable for 25mph running after the 2 week running in session in the Spring.
This easterly view (30/11/02) shows the tamper parked with the ballast train and Upnor Castle south of the stop blocks at Waunfawr. It appeared that most of the track had been tamped between Betws Garmon and Waunfawr. Click on the image to enlarge. This image is copyright B W Hughes taken on a Hitachi D8 digital camcorder VM-D865LE 230. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Plans to deliver the new tamper from Glan-y-pwll to the WHR by 16/10/02 reached their conclusion. The unit will be put to work on the section south of Waunfawr to test out procedures off the running line. All rolling stock stabled on the section was shunted on 5/10/02 to make space for the test. The unit was noted stabled at the Betws Garmon railhead w/e 20/10/02.
The WHLR Ltd. has set up a small tamping team. During the week ending 17/11/02 they have been placing 'top up' ballast along section from Waunfawr to Betws Garmon and preparing the new tamper. Volunteers have also done some manual horizontal track alignment in preparation.
Apparently, the tamper has been tested to 4" of tilt without toppling over. However, the packing gangs were requested to pack the track up where one of the rails was more than an inch lower than the other rail. If both rails dipped by the same amount, the track does not require attention.
The first tamping pass is to lock track horizontally and get some ballast up under sleepers to hold the track in place. After that the track will be lifted and canted during a second pass to tamp and pack the track in its final position.
The tamper was finally noted at work by 26/11/02 and initial impressions were very favourable. The trackbed appeared to be ballasted and tamped the full length to Betws Garmon by 1/12/02.
September Visits
September sees an innovative new event. There will be a visit to the railway by HSB (the German narrow-gauge Harzer Schmalspur-Bahnen) on 20-21/9/03. They will be crewing trains (under supervision presumably!) on both the FR and WHR. A return fixture has also been mooted! Steam Railway Magazine is also discussing a weekend visit that will receive advance publicity in the magazine as they have done with the Great Central Railway. The visit is on a 'to be confirmed basis' depending on the opening to Rhyd Ddu going through!
Bent Rails
The WHLR ordered a fresh batch of 640 rails which left Durban on 9/8/02 and was delivered on 19/9/02 (eventually to be split between Tros-y-gol, Plas-y-nant, Snowdon Ranger and Rhyd Ddu bases). The trackbed has been widened just south of LC51 at the north end of Snowdon Ranger Halt to take delivery.
However, this batch was sent to a Wolverhampton rolling mill (Barnshaws) for straightening as it was clear they had been mishandled in South Africa and were distinctly bent at the centre probably by being suspended from one central sling rather than two at the 1/3 and 2/3 positions along their length as normal. Some 50% of the total order needs to be re-rolled following an insurance claim. The Snowdon Ranger delivery will be of lower priority now it has been decided to make Plas-y-nant top priority. Some of the less damaged rails have been used at Salem and Rhyd Ddu.
The shippers' insurance cover has now settled the claim and at the turn of the year, the first third of those needing to be re-rolled had been completed at Wolverhampton and were awaiting return to the railway to be delivered to Snowdon Ranger. Some 12 lorry loads in all will be making the return journey.
Rails will be laid north from Snowdon Ranger to Castell Cidwm following completion of the ballast bed to Snowdon Ranger w/e 6/10/02. John Sreeves (in a valiant solo effort) laid out sleepers south of Castell Cidwm from Ch.11120 to Ch.11250 over the weekend ending 6/5/02.
Rails were arriving w/e 22/9/02. The Waunfawr stockpile was exhausted as all the rails and some Dinas supplies have been moved to Cae Hywel but has been replenished by new deliveries. About 0.75km of track remains at Dinas.
The tracklaying gang will have a long post Christmas session 27 - 31 December, then 11/12 January and fortnightly from there on. They are still trying to establish a separate gang for the other weekends. Volunteers are welcome (contact Jan Woods-see above).
Caernarfon Ticket Office delay
The new ticket office/retail area for Caernarfon initially ran foul of planning/siting arrangements. It cannot be by the buffer stop in case the train overruns. A new position near the car park access has been proposed to GCC for consideration at the April planning meeting. A new car park access would be constructed nearer the roundabout. The aim is to make the train more visible to members of the public to attract more travellers.
Work could start soon as all planning permissions were received in May 2002. The decision about a Waunfawr building has still not been taken. A coach bay will also be constructed at Caernarfon as the number of booked tours is expected to increase considerably after opening to Rhyd Ddu next year.
Video Links
With the arrival of a new digital video camera and the installation of Studio DV on your webmaster's computer, you may now view clips of video directly. The Hitachi video camera can also digitise previous 8mm and Hi 8 (stereo) recordings.
To make the file size appropriate (and download times manageable), the chosen format is RealMedia. You will need to download the free Real Player 8 Basic. The link is at the bottom right of the first Real Player screen and on the grey bar about halfway down the second screen.
Click on this link for Real Player
The second file uploaded is a 20 second view of No. 143 passing through Cae Moel bridge in heavy snow on 31/1/01. The file is 0.5 MB long and will take up to 5 minutes to load at 56k.
Click here for Snow scene clip
A library of clips will be made available. Please email me and let me know what you would like to see in the library.
Level Crossings named
Several Phase 1/2 accommodation crossings have acquired names. These have been marked into the wooden gateposts to help staff identify where they are. Those noted so far are:-
Pant Farm (south of Hendy l/c)
Fron Goch (Garden Centre)
Cae Goronwy (just south of landslip)
Cae Bryn Siriol (west of Cyrnant)
Cyrnant
Cae'r Afon (just before Waunfawr)
Temporary fences have been erected across the newly laid track by persons unknown between LC26 and LC27, on the new section of line south of Waunfawr, presumably to control sheep wandering on the railway.
Heritage Diesel Fund launched
FR members have launched a fund to repair the Kerr Stuart 6wDM diesel shunter (6 wheel diesel mechanical chain driven) that was trialled on the WHR in 1928 and must have travelled through the Aberglaslyn Pass as it worked on the FR in 1929. The loco was returned to its builders who regauged it for trials on the Castlederg & Victoria Bridge Tramway in Ireland before it was regauged back to 2' for export to a Mauritius sugar plantation. The loco was returned from Mauritius in 1997 and is stored under cover at Minffordd Yard.
As well as appearances on the WHR/FR, the intention is for the loco to visit 60cm gauge lines in the UK and Northern France. It is estimated the loco will cost around £50,000 to restore if done professionally.
The 4415 Group has already obtained a replacement for the 1945 power unit and intends to restore the loco to WHR condition, perhaps at Boston Lodge. Those wishing to contribute should contact the 4415 Group at 31 Caernarfon Road, Stratford, London E15 4JW.
For further information click on the email link below
mailto:meridianmodel.rosa@talk21.com
WHR 'Spotter's Guide'
The FR has released Spotter's Guides for both the WHR (50p) and the FR (75p). They are aimed at children and do not provide a full listing of rolling stock but in the WHR version all the locos and coaches are listed with some examples of works train stock. Lineside features are also listed with a map of the route. Copies can be obtained by post from the FR at Harbour Station.
Castell Cidwm bridge
Work on OB 71 at Castell Cidwm began w/e 20/10/02. The site has been accessed from the main road north of the bridge and cleared. A concrete chute has been erected on the south east side of the bridge. This bridge received waterproofing attention from GCC a few years ago, however, some underpinning is necessary to gain the additional clearance required by the Funkey/Garratt loading gauge. The trackbed has been cleared to the end of the WHLR subcontract from Snowdon Ranger.
Drainage has been a major problem here as well as access. Jones Bros. have built bunds to prevent ingress from the Snowdon Ranger direction and are pumping water around the site.
The site was cleared and progress was being made with the trackbed during late November suggesting the underpinning works were complete, though they may have been abandoned awaiting better drainage.
The contractor hit rock in the floor of the northern approach cutting to this bridge whilst lowering the formation and preparing to dig a deeper ditch (right) to drain the low point under OB71. Due to the difficult ground conditions under this bridge an alternative method is being developed for lowering the formation and underpinning its foundations. Jones has withdrawn its mess-room for the time being.
However, by 23/12/02 a hydraulic rock pecker had been in action and the level and drainage was nearly complete in the area shown below.
This northerly view (23/12/02) shows the cutting now excavated through glacially smoothed solid rock, which was found when the trackbed was scraped clear of mud just north of OB71. A hydraulic rock pecker has been used for this and was still on site on this date. The key point has been to excavate the ditch (right) which is needed to drain the dip under the road bridge. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Construction progress south from Snowdon Ranger Halt
W/e 1/12/02 it was clear that most of the drainage and bridgework had been completed on this section. Some 130m north from Glan-yr-afon viaduct to UB93 had been completed with rolled slate fines angled for super-elevation on the curves and for drainage. However, UB90/92 both needed re-decking at Bron-y-fedw Uchaf, just north of this point.
This northerly view (1/12/02) shows the recently completed trackbed at Bron-y-fedw Uchaf with Llyn Cwellyn in the background. The drainage has been completed and the trackbed stabilised. The ballast retaining walls of UB93 are visible under construction at Ch. 12480. Slate fines have been rolled with a camber on these sharp bends to provide super-elevation and aid drainage. Click on the image to enlarge. This image is copyright B W Hughes taken on a Hitachi D8 digital camcorder VM-D865LE 230. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
By 31/12/02, the final rolled formation consisting of slate fines had been completed all the way to Ch.11487 just south of Snowdon Ranger, except for a short section at Bron-y-fedw Uchaf where an underbridge (UB90) requires re-decking. Ballasting has also been completed on the section from Glan-yr-afon Viaduct to Ch.12450 at Bron-y-fedw Uchaf. Sleeper packs have also been laid out on the ballasted section. The stonemason is also at work building up headwalls to retain ballast on several underbridges.
This northerly view (31/12/02) shows the trackbed now ballasted in the same position at UB93 as shown above. In the background is Llyn Cwellyn. Sleeper packs have been laid out along this stretch. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The site of Snowdon Ranger Halt was cleared by 19/8/02. The halt is to have an asphalt platform and a replica waiting shelter similar to the one built by the WHR(Porthmadog) at Pen-y-mount, based loosely on the original Nantmor Halt.
A week later the WHLR subcontractors had built up and levelled the site and were advancing towards Glan-yr-afon. By 23/8/02, the trackbed had been consolidated to Ch. 11535 where culvert UB82 was having a reinforced concrete slab deck added.
Trackbed works had advanced to Ch.11960 by 14/9/02 with the end of work in sight some 700m (under half a mile) further on at Ch.12600 (Glan-yr-afon Viaduct). Some works remain to be finished on the Castell Cidwm to Snowdon Ranger section though, including LC46 and the formation over UB73.
'Snowdon Ranger' (the WHRS magazine) has revealed details of the proposed waiting shelter at the halt. It will be 2m x 6m approx. with a slate roof and windows to the front and in the end elevations, with a central access. The building will be erected on a blue brick plinth with a concrete floor that drains towards the platform.
There will be a full length bench along the back wall of the shelter, though provision will be made for the southern third of the shelter to be partitioned off for a possible Token Room or Storeroom. The platform face of the building will have notice boards either end for timetables and information.
WHR 2003 timetables available
It is intended to launch the Plas-y-nant service from 14/4/03 in time for the school Easter holidays if the line is ready but without platforms. Rhyd Ddu might be opened on 30/6/03 if all is well. The spare time might be used up in slow running and/or running back to Waunfawr and standing there, rather than at Plas-y-nant. Three sets of points are ready for Plas-y-nant loop and Rhyd Ddu. One set is already at Rhyd Ddu for the loco siding.
There will be a two train service with the modern 7 coach Eryri Express rake formed of the 5 saloons and the refurbished Pullman Bodysgallen and an Open coach. The second rake (up to six coaches) will feature Nos. 100/121 from the FR fleet, given a tidy up and a lick of paint. The FR coaches provide the basis of a second corridor connected rake including brake and first class travel. Further FR coaches may be moved to the WHR if traffic demands. The two heritage coaches Nos. 23/4 will be used in peak times on either rake. The two new Opens will also be available.
With the Xmas school holidays extending over 2 weeks, the WHR has decided to extend its two train service into January. The 2002 service duly closes on January 5th. The two train steam service (1030 and 1315 departures) operates from 26/12/02 to 5/1/03 with heated coaches with Xmas decorations. The timetable leaflet features the FR timetable on the reverse side.
The railway will operate weekends in January, following suggestions that the WHR will become a round the year operation. Tourists have previously turned up on fine January weekends and been disappointed that there were no services. The diesel hauled service will operate twice a day until Half Term (15/2/03 to 2/3/03), when a steam hauled daily service will operate with the same timings. This may aid grant applications for the completion of the through route.
| Caernarfon | 1130 | 1330 | 1510 | |
| Dinas | 1145 | 1345 | 1525 | |
| Waunfawr | 1205 | 1405 | ||
| Waunfawr | 1220 | 1420 | ||
| Dinas | 1040 | 1240 | 1440 | |
| Caernarfon | 1100 | 1255 | 1455 |
The full timetable for 2003 is now available on the FR timetable site.
Plas-y-nant loop will feature initially as a run round loop but with no platforms in 2003, so it will not be possible to change trains there. Dinas and Waunfawr will be used to pass trains. Snowdon Ranger does not appear in the timetable either but with its Halt status, if opened, its timings could be expected to be about 10 mins before/after Rhyd Ddu.
Trains are allowed 25 mins for the additional five miles (including a request stop at Snowdon Ranger). Most take 2½ hours to do the round trip, though the 'early bird' 0850 (peak weeks only) diesel service does it in 2 hours 10 mins. Most trains take 20 minutes at Rhyd Ddu for the run round.
There are four round trips in the Gold (near peak) timetable and six in the peak Red timetable, including a 1630 Eryri Express. However, the current 1655 and 1805 services have been dropped as uneconomic in view of the poor loadings and later return times. Trains pass at Dinas and Plas-y-nant in both timetables.
The Gold timetable shows both steam locos doing two return trips but the Red timetable is unusual in that the second steam loco picks up the 1130 diesel working of the Heritage rake on its return to Dinas at 1340 and does only one round trip on the 1430 from Caernarfon! Meanwhile the Eryri Express makes three round trips with the same loco.
Progress south from Plas-y-nant
Tall sign poles have been erected at Plas-y-nant (and at Rhyd Ddu) presumably to identify the Millennium Project and the two station locations. There was no signage by 23/2/03 at either location.
On 19/9/02, the WHLR took delivery of its final set of rails from South Africa. The delivery came via lorry in several loads from Bristol Docks, rather than Immingham as previously. The 640 rails have been stored at Waunfawr and a new site just south of the car park at Rhyd Ddu. The arrival of the rails completes the delivery of all track materials required to finish Phase 3 tracklaying works. Altogether some 5760m (3.6 miles) of track can be laid using these 18m long rails.
This northerly view (30/10/02) at Ty'n-y-werglodd cutting shows the completed fencing and basic clearance through this section. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
This northerly view (26/1/03) at Ty'n-y-werglodd cutting shows the completed ballasted trackbed with bundles of sleepers ready for volunteer tracklaying. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
By w/e 27/10/02, a rail stack had been established at Plas-y-nant, ready for tracklaying south from that location. However, a week later there had still been no delivery of rails to Snowdon Ranger despite the availability of the trackbed.
This southerly view (30/10/02) at Plas-y-nant shows the large rail stack and ballast pile alongside the trackbed. In the distance a ballast pile is visible but only a short length of the loop has actually been ballasted from Ch.9330 to Ch.9390 of the westerly (Up) track. This leaves space for dumpers to drive to the work beyond to Ty'n-y-werglodd cutting, which is just getting underway. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The section of route north from Castell Cidwm was pegged out by 24/11/01 and some fencing was underway. This section will be built by a sub-contractor. The work means that there is now progress on all parts of the route between Waunfawr and Rhyd Ddu (except Snowdon Ranger to Glan-yr-afon).
A base site was established at Plas-y-nant in the first week of July. However, after initial clearance of the area between the main road and the railway immediately south of the Afon Gwyrfai bridge, work came to a stop by 12/7/02 as a void opening on the roadside. Nevertheless, some progress was made with the Gwyrfai bridge and clearance of the trackbed north through the Gwyrfai gorge.
Plas-y-nant Halt will be constructed as two side platforms as at Dinas but only 60m long. The platforms will be over 100m south of the road entrance. Footpaths will run either side of the line to provide pedestrian access from the main road UB64. These will also provide a good vantage point for photography.
The Plas-y-nant loop will used as the run round loop for the Easter 2003 timetable though trains will not pass there in the full Rhyd Ddu timetable. It does not appear that there will be platforms for 2003 and so it will be impossible to change trains here.
A concrete access from the road was constructed by 7/8/02 and work started widening the formation on the northern half of the loop. GCC was digging up the road to deal with the hole from 12/8/02 and traffic lights were present. Some tipping to widen the formation has already occurred at the north end of the loop and the pile of rubbish that has obstructed the alignment for several years has now been bulldozed.
Although work clearly extends south from Ch. 9500, basic clearance has only appeared from the cutting at Ch.9800 onto the Castell Cidwm straight during November. Clearance work appears to have reached the end of the cutting by w/e 13/10/02. Work was underway between the cutting and Castell Cidwm bridge during November 2002, deepening the ditch on the east side to better drain the bridge underpinning works.
The dispute with a local farmer over access and fence lines over the 200m section south of Castell Cidwm bridge has been resolved and now it can be truthfully said that work is underway over the whole line. By w/e 24/11/02 work was in progress extending the sub-base over the northern 100m of this short section from Ty'n-y-Weirglodd cutting. The conditions were very boggy initially.
Dinas overbridge re-opened
Dinas overbridge at the south end of the station was closed for strengthening work during the Autumn by GCC. Access to Dinas was restored during December. The ex-LNWR structure was originally built by the Caernarvonshire Railway and was almost 150 years old. It had been fitted with smoke deflectors to prevent acid attack on its decaying structure. A weight restriction had been in force for some time.
This southerly view (23/12/02) shows the newly reopened Dinas overbridge. A concrete slab deck has been constructed over the railway on the existing abutments following removal of the decaying original jack arch structure. Unfortunately, rules for new construction will mean the loss of this vantage point as the bridge parapet is being increased in height. However, it appears the concrete side walls will be lower. These will be clad in local stone. It is uncertain if the smoke deflectors will be reattached to this bridge as other concrete bridges do not have them. Temporary signs indicating the diversion of the Lon Eifion cycleway will be removed shortly. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Work underway on Waunfawr points
In December, work was underway on installing an automated point mechanism on the Waunfawr loop south points. A point has also been moved to the south end of Plas-y-nant loop. However, Plas-y-nant loop will initially be hand point operated. These points will be locked out of use following the short period between their Easter opening and the subsequent opening of the whole line to Rhyd Ddu.
This southerly view (30/12/02) shows work is underway on the point at the south end of the Waunfawr loop. The point was initially hand worked but is being automated with the usual indicator lights. Beyond the limit of shunt, Upnor Castle is stabled on the new line with the PW train. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Betws Garmon missing link
Clearance work has started on the short section from Bryn Gloch to Betws Garmon. Work began w/e 20/10/02 and basic trackbed clearance has proceeded south from LC30 (just south of the Afon Gwyrfai bridge) over UB52 and through the completed OB53 main road bridge.
This northerly view (30/10/02) from OB53 shows the progress approaching UB51. The tamper is also visible stabled at Betws Garmon station awaiting parts. It was receiving attention on 2/11/02 and may have been moved a little north. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
When the trackbed is consolidated, ballast will be trucked in to extend the ballast bed north from Bryn Gloch to LC30. Track will then be laid over this 150m stretch leaving just the short section either side over UB51 to be completed when the bridge has been placed in February. The De Winton girder for the south side of OB53 has still not been erected despite the contractors having cleared the site.
By w/e 27/10/02, the formation had been correctly profiled for the dip under the main road at OB53 and slate fines rolled to form the trackbed. Ballasting is imminent. However, this section was badly flooded under OB53 and work will entail installing a deep drain before progress can be made ballasting.
This southerly view (30/10/02) shows the flooded (40cm deep) trackbed through OB53. A deep drain may need to be constructed through the bridge. It was probably the intention to get tracklaying underway on this section in early November as rails had been moved north of Bryn Gloch and laid in the two foot in preparation. OB53 still needed the parapet capping blocks above the railway and the southern De Winton girder erected. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Flooding increased after the above views and it was essential that a deep drain be established to make sure this location remains dry. By w/e 17/11/02 the slate coloured capping blocks on the parapets over the railway lines were being fitted and it only remained to fit the remaining De Winton girder to the south face of the bridge. Apparently, the ledge is not satisfactory.
This westerly view (24/8/02) shows the completed north face of OB53. The cladding of the railway faces with riven slate has been completed. The grey stone walling of the concrete in the railway slot was complete but the sharp slate capping on the parapet was still not complete. This is added to deter walking on the parapet. Click on the image to enlarge. This image is copyright B.W.Hughes. Digital image from Samsung Digimax 230, post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
In early December 2002, GCC contactors undertook remedial work to remove the recently applied local stone cladding within the railway slot on the west abutment to improve clearances. The cladding disguises the bridge's concrete structure. A thinner cladding layer was applied the following week.
This explains why the WHLR's works through the bridge have been stopped for two months since being handed over in October. Work appeared complete on the re-cladding by 15/12/02 so WHLR sub-contractors may return to the site before the end of the year to deal with the drainage and allow ballasting and tracklaying to be completed through the bridge from the Head of Steel at Bryn Gloch at Ch.7240.
This southerly view (30/12/02) shows that the trackbed has flooded badly again at Pont Betws. However, when GCC has completed the drainage in January, work will proceed to complete the ballasting and tracklaying with wooden sleepers under this bridge. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi
While the works under UB 53 were flooded during October and November, on 23/12/02 an excavator was present tidying up. Although the area under the bridge was dry on that date, by 30/12/02 it had flooded again. GCC is responsible for the completion of the trackbed through the bridge in return for the WHR allowing use of its hard standing for access. This means the extension north from Bryn Gloch is available once ballasted early in the New Year. Flooding was still apparent on 26/1/03 as the drainage work had still not been completed.
This northerly view (30/11/02) shows the flooded trackbed immediately north of the Head of Steel in Bryn Gloch at Ch. 7240. Click on the image to enlarge. This image is copyright B W Hughes taken on a Hitachi D8 digital camcorder VM-D865LE 230. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Afon Glaslyn Footbridge at Bryn-y-felin
Work started on the new Bryn-y-felin footbridge w/e 24/2/03, following completion of funding arrangements in November 2002. Initial work included clearance around the site of the new abutments. It was originally proposed that the bridge be completed last year. The bridge is a joint venture between WHLR/SNPA/NT but will be co-ordinated by the WHLR. It is the intention to build the bridge a few metres upstream from the position of the railway bridge. Posford Duvivier has been instructed to take the project forwards. Colin Jones (Rock Engineering) of Porthmadog has won the contract.
The new bridge will reconnect a footpath route lost when the Bryn-y-felin railway bridge was closed because it became unsafe about five years ago. This will allow circular walks from Beddgelert via Gelert's Grave and both banks of the Afon Glaslyn. It also permits a walk from Nantmor NT car park via the difficult Fisherman's Path and back via the main road.
The new bridge will be sited to the north of the existing abutments. The footbridge may also offer new vantage points for railway photographers when Phase 4 is opened in 2005/6. It is to be constructed using two curved steel beams cased with timber side rails. Each end will be on raised abutments with a slope connection into existing footpath network making it suitable for disabled users (wheelchairs).
The delay in the construction of the footbridge is for financial reasons. In April 2002 Beddgelert Community Council was advised that costs had risen by 40% from the original £63,000 to £88,000. This was as a result of a request to Gwynedd Council to adopt the new bridge as a Public Right of Way. The status of the footbridge has been agreed but the design must now conform to more stringent Bridge Code specifications explaining the increase in project costs.
Commitments were being sought from the various bodies contributing to the planned bridge, to meet the higher costs, and the SNPA has agreed to increase its contribution to meet 20% of the £25,000 extra costs. The June 2002 meeting of the Beddgelert Council reported that funding was now complete and that work would go ahead shortly. Some examples of paving for the disabled access path from Beddgelert to Bryn-y-felin were on display for comment by the Beddgelert footbridge during August 2002.
Beddgelert Community Council stated in their report of November 2002 that a grant application had been made to the Rural Recovery for Tourism Fund for the remaining shortfall. Following receipt of the grant, a start date of January 3rd 2003 was suggested for the footbridge construction works.
The National Trust, the landowner, was building improved paths, suitable for wheelchairs, leading to the footbridge site in November on either side of the Afon Glaslyn. These initial works were expected to be completed by 18/12/02. The works would include removing the kissing gate in the former east abutment of the PBSSR Glaslyn bridge.
This northerly view (30/12/02) shows the completed hard path from Beddgelert to Bryn-y-felin complete with 'passing loops' for wheelchair users! A considerable mess has however been made of the meadow to the left. The path remains incomplete at Bryn-y-felin as the bridge will be built first. Click on the image to enlarge. This image is copyright B W Hughes. Image taken on Samsung Digimax230 digital camera using iPhoto Plus4 image correction technology. Image displayed at 96dpi.
Contingency plans
The WHR Board has discussed contingency plans in case work is not complete in time for the proposed Easter 2003 opening to Rhyd Ddu. The route could be opened to the run round loop at Plas-y-nant, which would need completing contrary to current plans.
A lot of the final track laying, using a mix of volunteer and paid staff, as well as some of the final stages of the civils work needs to be undertaken in the depths of winter. It does not look like Jones' contract will be finished before 27/10/02 as planned. Progress depends on weather and a bad winter would naturally cause delay. Spending additional money now does not help either even if it were affordable within the project budget.
So the WHLR Ltd Board, in conjunction with FR Co. Board has evolved a plan to handle the construction delays. The full opening to Rhyd Ddu will follow the Easter opening to Plas-y-nant by May Bank holiday. Push pull operation to the railhead using an additional diesel shunt loco was apparently not considered. Such a loco could come up to Waunfawr on the first train of the day as it did before Waunfawr loop was completed.
Rhyd Ddu platforms under construction
A major step in the construction of Rhyd Ddu station was begun w/e 28/9/02 with the construction of the kerbstones for Rhyd Ddu platform. The 88m platform will be an island platform like Waunfawr. South of the station the trackbed has been excavated to Ch.14875 for the loop and headshunt, however plans suggest that this should be at least Ch.15000, back on the old formation alongside the main road.
This southerly view (31/10/02) shows the Jones Bros. worksite at the south end of Rhyd Ddu. A rail stack has been established here. Excavators are clearing a route around the rail stack on the west side (right) so that excavations can continue at the extreme south end of the station possibly while track is laid to the north along the ballast. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
By w/e 6/10/02 the formation had been completed through the easterly arrival platform though not yet across the access to Ffridd Isaf/Snowdon path LC65 to join with formation and track laid north of there in the Spring.
By w/e 13/10/02, the formation of the arrival track (easterly track) had been ballasted through the platform and the platform had been made up to its proper height with fill. The south end of the station has now been tidied up and the formation is complete in this area. The formation for the run round loop on the west side still needs to be made up and the platform edge has still not been finished. The formation has still not been completed across LC65.
By w/e 20/10/02, work was proceeding on the linking section of trackbed at the north end of Rhyd Ddu station across LC65. Much of the excavation appeared complete but only part of the large rock blocking the trackbed will be removed by a rock pecker.
This northerly view (31/10/02) shows the north end of Rhyd Ddu station. The trackbed drops steeply down off the platform as at Waunfawr and will produce some interesting chuffing as trains arrive! No further work has been done on the l/c (LC65). Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The platform appears to be 88m long approximately, terminating at a temporary southern end opposite the car park at Ch. 14777 approx.
This northerly view (30/11/02) shows the completed ballasting in the western trackbed at Rhyd Ddu and the positioning of sleepers prior to handing over to the WHLR at the end of the year. The platform still needs tarmac before hand over occurs. Click on the image to enlarge. This image is copyright B W Hughes taken on a Hitachi D8 digital camcorder VM-D865LE 230. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
By w/e 17/11/02 the ballast had been laid north from the platforms and either side of the l/c (LC65) to link with the existing formation north of Rhyd Ddu. A widened area of ballast immediately south of the l/c is where the point will go for the run round loop. The large rock just south the l/c has not yet been trimmed to clear the formation and it looks like expansion chemicals will be needed to split this rock due to the closeness to residences (as was done at Waunfawr).
By w/e 24/11/02 the west side of the platform had been ballasted but it is clear that there will be no platform face on this side initially. The ballast extends up to the rail store on both tracks but it appears that work south of there is continuing.
There appeared to be no further progress by w/e 1/12/02. However, some additional kerb stones were in stock, presumably for the platform crossing area at the north end of the station. The platform is not yet tarmaced. There will be a separate contract for the station building.
Another planning application for the station building went in on 18/12/02, presumably to a different design. The SNPA had previously rejected the wooden structure proposed as they wish all new construction to be essentially in local rock finish in keeping with other buildings in the area.
This southerly view (23/12/02) shows the recently completed fencing at Rhyd Ddu Station. The station building will be built in the compound to the right. A 2m wide gateway in the fence gives access to cross the adjacent run round line and access the platform. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Work started at Rhyd Ddu on 15/7/02. A work camp was set up on the old formation immediately south of the car park where lorries had previously arrived delivering rail. Jones Bros. then set about carving a plant road at formation level around the Deviation along the west side of the formation where the run round loop will lie. By 17/7/02 this had reached the north end of the site where the transformer pole was recently moved to the side of the alignment. Some work had also been done scraping of the rock to the east prior to excavation.
By mid-September, the north end of the site was largely complete except for the level crossing, though signs of realignment of the fencing were apparent there too.
The wooden station building proposed by the FR has been rejected by the SNPA and a smaller stone building in keeping with the local character is likely. The road between the existing GCC toilet block and the level crossing will be diverted to the west side and 20 car park spaces for railway use will be provided on the east side. Despite the planning set back, Michael Whitehouse assured WHRS members at the AGM that the station building would be ready for the Spring 2003 Opening.
This northerly view (30/12/02) from the now fenced station building compound shows the position of the north loop points and the steep gradient into the platform as the alignment rises over a metre above the former levels in the SNP car park. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Initial clearance work has been done south of Ch.14800 and by w/e 17/8/02 work was underway between Ch. 14800-900, south of the car park. It is intended to construct the line as far as Ch.15200 to allow a whole train length south of the run-round loop headshunt. It looks like the whole Deviation can be constructed without blasting.
By 7/9/02 the north end of the station cutting had been completely regraded and the temporary peat bank spread on the cutting sides. UB116 was laid in by the end of August. Slate fines were being dropped north form Ch.14800 to establish final formation levels. Riven slate was delivered for culvert headwalls and dumped on the site of the future station building by 7/9/02. An additional culvert was being finished between LC65 and UB116 on 14/9/02. At the south end of the station work was approaching Ch.15000 at the extreme end of the widened section of fencing.
A wet August (with rain on about 50% of the days) delayed progress on the Deviation. From 13/8/02 spare material was being trucked up the Snowdon track for disposal and to improve the track.
A final decision has now been made about the nature of the temporary terminus at Rhyd Ddu. An island platform will be constructed at this location wide enough to take a passenger shelter. The asphalt platform will be 6m wide at the north end to allow for the shelter, tapering to 4m wide at the south end. Initially, only the 6m wide northern section some 90m long (enough for a seven coach train) will be constructed to reduce costs, though the full size loop will be constructed.
No footbridge will be provided. Passenger access will be at the north end of the platform. Whilst the station remains a terminus (possibly for 1-2 years), trains will run into the eastern side of the loop so that only the engine running round will cross the passenger access route. This will mean left hand running initially.
Ultimately right hand running will be the norm as at all the other passing places. A station building will be provided almost opposite the present toilet block but at a slightly higher level. The railway formation will be completed at this stage at least as far as Ch.15,200 (the nominal end of Phase 3). There were plans for a set-back siding for stock stabling along the east side of the run round loop. This has now been shelved to cut down on excavation volumes but could eventually be added. However, a siding may be built in the near future for Phase 4 construction trains. This 80m siding would be on the old formation north towards the car park from Ch.15,000.
Driver Experience Trains
The possibility of a new venture for 2003 was revealed at the WHRS AGM on 14/9/02. Driver Experience courses may be run using the freight rake and the Chattendon coach. As well as acting as a brake van, No.1001 can carry the family of the trainee driver and even provide refreshments. With K1 and the Garratts available, this could be a real money spinner for the WHR(C).
This northerly view (14/9/02) at Dinas shows No.143 shunting its mixed rake back out of the bay platform. This is one of 3 steam locos available for driver experience courses next year hauling freight wagons. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
WHR(P) progress at Pen-y-Mount
The WHR(P) is making progress with the 2.5km Pen-y-Mount Ch.33550 to Pont Croesor section Ch.31050. It is their intention to build this in two phases :-
Phase 1 Pen-y-mount to Traeth Mawr
Phase 2 Traeth Mawr to Pont Croesor
While Portreuddyn is the site of a former Croesor Tramway loop, it is the intention to construct a temporary loop just south of this location due to a land ownership issue. The project costs are estimated to be some £400,000 and coordination with the WHLR has been good with site visits by the WHLR Manager/Engineer from 1/7/01.
The WHR(P) received one of the Dinas points from WHLR recently and constructed the crossover at Pen-y-Mount during their Civils' Week from 27/7/02. As well as providing access to the 'main line' of the WHR, the crossover also provides a headshunt/trap point for shunting WHR(P) internal services clear of the future WHR main line.
Phase 1 will finish at 'Traeth Mawr', some 800m north of Pen-y-mount where there is an issue about trackbed ownership. For further details see the Pont Croesor to Pen-y-Mount page.
This southerly view (25/8/02) from LC121 shows good progress with the Pen-y-Mount crossover, which was laid w/e 4/8/02. The 'main line' runs to the left of Pen-y-Mount Halt visible in the distance on the left. A public footpath runs along the east side of the trackbed. The former WHR(P) headshunt at this location has been replaced by two points which will protect the main line form 'internal' WHR(P) movements when the through route to Porthmadog is opened around 2005. The further point will give access to the new WHR(P) headshunt which will run alongside the nearer point as far as the mound of gravel to the right. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The WHR(P) will apply for planning permission in the Spring of 2003 and is now fund raising to complete the line and open to Traeth Mawr in 2004. The plans are being finalised, and will cover the section of trackbed from Pen y mount to the level crossing at Pont Croesor. The delay has been caused largely by the Environment Agency, who needed to undertake a flood discharge study to work out the sizes of culverts required through the railway's embankment.
Click here for John Sreeves new map showing progress on this section.
Carriage shed pit underway
The FR has commissioned work on a 8m long carriage maintenance pit in the Dinas carriage shed. The carriage shed has been taken out of use while work proceeds. The pit is in the track nearest to the main line and is positioned close to the south entrance. A concrete floor and sump have already been constructed. The excavation has been plagued with flooding on occasion but should be complete in August so that coaching stock can be maintained inside this Autumn protected by the weather.
The right hand road was reopened by 24/8/02 but the pit road was still not relaid on 28/9/02.
This northerly view (2/8/02) shows the contractors lining the excavation with breeze block walls. Work started in early July. Rails have been removed from the track nearest the main line. Click on the image to enlarge. This image is copyright B W Hughes. Image taken on Samsung Digimax230 digital camera using iPhoto Plus4 image correction technology. Image displayed at 96dpi.
The carriage shed has made some progress during recent months. The steel work is all securely fixed down and the first section of the concrete apron round the pit has been cast so securing the lateral ties on one side. The rest of the apron will be finished early in the New Year, followed by the lights and the final packing of the rails. As the rails are now secure all the carriages are now kept inside at night, with Road Two being used for the operational set.
Contracts are also being prepared for Glan-yr-afon Viaduct (OB64). The 'transom beams' are the transverse beams joining the two principle structural girders and are to be replaced. The main beams are fabricated from wrought iron. The principle components are the top and bottom flanges and the web plates which hold them apart. Because the web plate is 96ft long and 8ft high it obviously is made from several plates joined together.
In practice these plates are each about 8ft square and are joined together by two flat strips of wrought iron (splice plates) riveted either side of the join to show two vertical rows of rivet heads. In some locations one of the splice plates is replaced by a 'T' section member. These flat strips and 'T' sections are considered to be insufficiently strong and are to replaced by stronger steel members with larger rivets. The abutments will also be refurbished.
All the work to the wrought iron beams of the Glan-yr-afon viaduct will be done in situ with the splicing plates being replaced one at a time. Scaffolding will be hung from the bridge to allow workers access to all parts. Work started in July with scaffolding due to be erected by 12/7/02.
Viaduct Progress
On 8/7/02 work started on Glan-yr-afon Viaduct. The first job was erecting the scaffolding that will hang from the viaduct to give Jones Bros. access to the beams. The bridge will feature new steel splicing plates to join the wrought iron plates that form the web of the original main beams. Replacement of the original cross bracing with steel members is also required to strengthen the structure for the heavier modern trains. Michael Whitehouse confirmed at the WHRS AGM that the viaduct will be able to carry double- headed Garratts.
A small Caernarfon company, Brunswick Ironworks, is making the new steel parts. The same company has also provided the bases of the Caernarfon and Waunfawr water towers, and the steel structure of Waunfawr footbridge. The WHLR remains committed to placing work with the local companies to benefit the North Wales economy. Jones Bros. will be based at a worksite at the north end of Glan-yr-afon Yard. For more details of the Viaduct project see below.
By 12/7/02, the rotten wooden waybeams had been removed to the south end and cut up with a chainsaw. Scaffolding had been erected to give a walkway across the viaduct on the west side. Scaffolding had also been erected on the outside of the main west girder to allow access for the removal and replacement of the splicing plates (one at a time!).
This northerly view (12/7/02) shows progress on Glan-yr-afon Viaduct. The waybeams have been removed (pile right) and a scaffolding deck constructed across the bridge and outside of the main west girder too. This was the main task that needed to be completed before Jones Bros. could start removing splicing plates and fitting new stronger steel ones with larger rivets. The east girder will apparently be treated second. Access is from Glan-yr-afon yard as a steel barrier has been erected barring the north end of the bridge. Click on the image to enlarge. This image is copyright WHLR, courtesy Jan Woods. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
This southerly view (25/7/02) shows progress on Glan-yr-afon Viaduct. The scaffolding is almost complete and a lower level plank-way can be glimpsed giving full access to the inner side of the main beams from where Jones staff will replace the splicing plates. Click on the image to enlarge. This image is copyright WHLR, courtesy Jan Woods. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Work on the viaduct itself had not started by 2/8/02 as there were ongoing discussions between Jones Engineers and WHLR Consultants Posford Duvivier about the best method to strengthen the viaduct.
Work on the repair of the abutments was completed by w/e 17/11/02.
Timetable proposals for Rhyd Ddu
The WHLR management believes a summer opening to Rhyd Ddu is now much more certain following recent good progress with bridges and tracklaying. However, the Easter opening to Plas-y-nant is now less likely and the railway may open to Rhyd Ddu as a single step extension around June 28th.
With this is mind FR timetables have switched to 'Plan B'. The latest WHR timetables shown on the FR website show trains terminating at Waunfawr until a 'Special Service' extended to Plas-y-nant in the Spring Half Term Holiday week commencing May 24th. Details of this service will be announced in due course. However, as the following service from May 31st. allows only 5 mins at Plas-y-nant for run-round, a diesel shunt loco is possible based at Waunfawr as was operated at Waunfawr before completion of the loop there.
Subsequent weekends from May 31st. show 5 trains going to Plas-y-nant commencing with the 1030 service. The 1200 and 1500 are diesel services. Trains normally pass at Dinas but the final train of the day at 1540 passes at Waunfawr.
The opening to Rhyd Ddu has been put back to July 26th, in time for the main school holidays. There will be six round trips, four hauled by steam. An 0850 diesel service kicks off the day from Caernarfon and provides an early 1000 northbound service from Rhyd Ddu for people staying in the Beddgelert area wanting a day out in Caernarfon. Some 10-15 minutes are allowed for running round at Rhyd Ddu. The 1030, 1330 and 1630 ex-Caernarfon are named trains, known as the 'Eryri Express', and will carry a buffet trolley service.
The 1130 diesel service changes locos on its return to Dinas and operates as a steam service for one round trip as the 1430 ex-Caernarfon. If traffic develops better than expected, its 1700 ex-Caernarfon return working to Dinas could be developed into a final round trip, possibly picking up a diesel from Dinas as last year. Trains pass at Dinas and Waunfawr in this timetable.
Timings for Plas-y-nant are 1hour or 55 mins and 55 mins on the downhill journey. The extension from Waunfawr to Plas-y-nant is timed at 15 minutes allowing for a slower speed through the tight bends on this section. When trains are extended to Rhyd Ddu, timings are 1 hour 10 mins or 1 hour 15mins, allowing a further 10 mins for the climb to the summit. Return times are 1 hour or 1 hour 5 minutes.
The downside of the timetable has been a considerable reduction in services in the Spring before the railway extends to Plas-y-nant. The FR believes that people will delay their visits until the extension opens. For example from 12/4 from 4 to 6 workings had been envisaged over Easter but only 3 return trips are now planned. Similarly in May, the four steam train service originally planned is reduced to 3 services at weekends and 2 diesel services in the mid week until 24/5.
Even after Plas-y-nant is opened, service reductions are planned, until the Rhyd Ddu extension is opened. Originally, four services were planned throughout June and until July 25. Now, although there will be 5 trains at weekends, only two diesel hauled trains will operate mid week.
The timetables for September and October are currently incorrect as some days still show the trains terminating at Plas-y-nant. However, September midweek operation shows two diesel services using one set but an enhanced weekend 5 train service is envisaged until 5/10/03 (2 diesel and 3 steam). The daily service continues to the end of October with the weekend timetable reducing to 2 diesel services from 11/10/03 and no special provision for the Half Term school holiday period.
The November and December timetables appear correct with trains shown through to Rhyd Ddu. The weekend only timetable shows two steam services until the end of the year. These also operate from 26-31/12/03.
Pont Betws and UB51 completion
Jones Bros. will soon complete drainage works through OB53 Pont Betws. A deep drain will be constructed to remove the water that frequently collects at this low point, discharging just north of the bridge on the east side. This will be followed by ballasting up to UB52 whilst leaving access to UB51 for placement of the bridge girders recently purchased and now under alteration to fit the gap. The new girders for UB 51 will probably be craned in from the level access at the Betws Garmon station site end (Ch.7000).
The ex-BR girders, believed to come from a skew bridge formerly at Tyne Dock, are easily capable of carrying WHR loadings. The girders for UB51 are 18.2m long and 1.7m high, welded steel plates with web stiffeners. The gap to be filled is 19.6m between the back walls of the abutments, so the beams will be extended by over a metre, leaving a 50mm gap for movement and tolerances at either end. Fortuitously, the width is exactly right to fit the abutments, although some local modifications to the bearing plinths may be needed to suit the bearing plates.
As the beams were designed for a skew bridge and the cross members have to go square across between the main girders, it is necessary to square off the ends. While the individual girders are long enough to span the gap, the position of the stiffeners prevents the girders being moved relative to each other. An extension of 1.14m will be required at the two diagonally opposed ends. The steel plate is 38.1mm thick and not amenable to welding so the best solution is to bolt the extension pieces on using splicing plates with lots of high strength friction grip bolts.
The deck consists of pre-cast concrete trough units. These weigh nearly 5 tonnes apiece, but their use will greatly simplify tracklaying, instead of having to fix the sleepers on to waybeams as at Plas-y-Nant. Only the wheels of the loco will be hidden inside the depth of girders, as the cross members, concrete deck and ballast account for over a metre of depth. The old girders were 15.94m long, and the clear gap between abutments was 14.6m, now widened at the request of the Environment Agency to 16.8m to cope better with floods. The new girders are likely to be painted black.
Progress to 23/2/02
Cladding has started on the completed abutments at Tros-y-gol bridge. The bridge girders have still not received their new cross beams but the bridge has been scaled and painted in epoxy silver undercoat except for small areas at each end where the bearing plates have now been cut off.
This westerly view (23/2/03) shows good progress with south abutment of Tros-y-gol bridge. Cladding is underway on the south abutment. The three metre deck will have a cosmetic central pier built in local stone in addition to cladding the river pier. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
At Plas-y-nant, the west girder has been scaled and painted with epoxy coating. Cantilever steel joists 1m long approx. now project out from this west girder to form the private footpath for the residents of Pen-y-gaer (also accessed via Pont Cerrig-y-rhyd).
This northerly view (23/2/03) shows good progress with Plas-y-nant bridge. All 12 sections of steel waybeam have now been fitted. Stiffeners can be seen wherever a waybeam rests on a crossbeam. The left (west) girder has been scaled and painted in epoxy silver undercoat. Cantilevered steel extension sections have been bolted onto the west girder to form a private footpath for the residents of Pen-y-gaer cottage on the hill to the left. They had previously established a wooden footbridge over the girders around 1995. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The trackbed at the north end of Rhyd Ddu has been marked out for the position of the left hand point that is soon to be installed there. Progress on this and completion of the loop may be made in two weeks time.
This southerly view (23/2/03) shows the position of the north end point at Rhyd Ddu marked out just south of LC65. Yellow pegs mark the completed survey. The arrival line will initially be the left hand running line and this will have a further sharp curve to the left as the point is laid out for right hand running into the platform for when the railway runs through to Beddgelert. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
A start has been made with laying track at Snowdon Ranger. Starting at Ch.11391 adjacent to the rail stack, 2 temporary panels were laid, followed by 9 permanent lengths to Ch.11389, crossing LC52. Volunteers are happy with the quality of the re-rolled rails though the odd one still shows a slight kink.
Permanent staff may continue with this tracklaying during the following weeks. The loco shed and loco Dolgarrog may be moved to Snowdon Ranger to assist with the propulsion of rails up the 1 in 60 towards Glan-yr-afon viaduct.
This northerly view (23/2/03) shows good progress with tracklaying across LC52, south from Snowdon Ranger. Glass fibre matting laid over the ballast and covered with slate waste for the l/c levels has been lifted to allow access for laying the track through the crossing. This was the limit of the Head of Steel at the end of the weekend. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
This southerly view (23/2/03) shows the two temporary lengths laid south from Ch.11390 adjacent to the rail stack at Snowdon Ranger. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The water main diversion at Castell Cidwm bridge seems to be almost complete with a new blue pipe installed. This is buried 1m under the deepened formation at this point. Completion of the works will allow Jones to complete the final section of untouched formation between OB71 and the end of the section from Snowdon Ranger at Ch.10140. there has been no further progress between Plas-y-nant and Castell Cidwm.
This easterly view (23/2/03) shows good progress with the water main diversion at Castell Cidwm. With this complete, Jones Bros. will be able to join up the formation to that all ready completed from Snowdon Ranger. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
WHR(P) progress
Work was underway in February clearing the gorse from the alignment up to 1km north of the existing Pen-y-mount terminus. Work has now reached the shelf that runs along the side of the Creasy embankment, a high sand wall that preceded the Cob. The railway alignment runs along a shelf on its south-east side. The location of the intended temporary loop for Phase 1 at Traeth Mawr has now been reached around Ch.32500. This section requires two cattle creeps. For full illustrated details click on Richard Beton's Pont Croesor website.
FR coaches for peak season
The FR has recognised that the Heritage train was frequently overcrowded last year. The second set this year will feature FR coaches Nos. 100/121 (in addition to NWNGR replica No. 24) which provide many more seats. The two FR coaches are currently being face-lifted at Boston Lodge but full refurbishment will wait until their return at the end of the season. They are likely to be delivered to Dinas before Easter.
Breakfast train
The 0810 peak service from Caernarfon to Rhyd Ddu (if it survives the timetable reshuffle) is designed to carry significant numbers of walkers and cyclists into the Snowdonia National Park and provide a breakfast service on the train. The train also offers a good return working as the first morning train from Rhyd Ddu at 1000 for those wishing to take a day out in Caernarfon. This recognises the large catchment area of Rhyd Ddu including the nearby Beddgelert Forest campsite.
Progress to 16/2/03
There is good progress with UB90 at Bron-y-fedw Uchaf. The bridge may be finished in March.
This southerly view (16/2/03) shows good progress with UB90 at Bron-y-fedw Uchaf. The former sheep-creep is being widened from 1m to about 2.5m to allow access by quad bikes. The nearer south abutment has been repointed and appears to have some concrete backfill. The north abutment is being rebuilt in reinforced concrete with local stone cladding. The track has been left unballasted over this length until the bridge is complete. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Plas-y-nant bridge has now had all of its new cross members installed. Eight of the 12 I beams that support the track have been installed but not yet bolted in position. They lie asymmetrically to the east on the outside of the curve.
This northerly view (16/2/03) shows good progress with Plas-y-nant bridge courtesy of a special site visit authorised by the WHLR and Jones Bros. All the cross members have been replaced with new steel versions. New I beams are positioned under the track and supporting the wooden sleeper ends. These are not yet bolted in position. The I beams have strengthening plates between the web and the top and bottom flanges at regular intervals. A third set of I beams will be installed at the north end of the bridge. Although the I beams were not completely bolted down on this date, the holes had been drilled indicating the railway would be positioned asymmetrically to the right (east), leaving a walkway on the left of the view. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
This northerly view (19/2/03) shows good progress with installing the I section waybeams at Plas-y-nant bridge. The beams have been fabricated by a local contractor and the final four black painted beams were unloaded and fitted on this date from the truck parked on the south abutment. Click on the image to enlarge. This image is copyright WHLR taken on digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Ballast at Bron-y-fedw Uchaf has reached from Ch.12140 to Ch.11610, close to Snowdon Ranger. Some 25 x 5packs of re-rolled rail have been delivered from Wolverhampton to Snowdon Ranger and have been stored on the trackbed on the site of the halt platform. Ballasting to Snowdon Ranger should be completed by 21/2/03 allowing tracklaying to commence south from Snowdon Ranger.
This northerly view (16/2/03) shows good progress with ballasting at Bron-y-fedw Uchaf (LC55 at Ch.12140). This will be the point of access where ballasting is carried back to UB90. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
This northerly view (16/2/03) shows good progress with ballasting approaching Snowdon Ranger at Ch.11610. Only200m remain to access the rail store on the site of Snowdon Ranger Halt at Ch.11400. The tracked vehicle represents the head o ballast. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
This northerly view (19/2/03) shows good progress with ballasting approaching Snowdon Ranger at Ch.11550 approx, just north of LC52. About 150m remain to access the rail store on the site of Snowdon Ranger Halt at Ch.11400 and it is possible track will be laid south from this point from 22/2/03. The tracked vehicle represents the head of ballast. The tripod and laser head shows laser levelling is being used on this section. Click on the image to enlarge. This image is copyright WHR taken on digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Rail has now been delivered to Snowdon Ranger Halt (Ch.11400). There are 28 x 5 packs of rail at Snowdon Ranger, enough for 1260m of track, sufficient to take the Head of Steel over Glan-yr-afon viaduct and meet with the Head of Steel from Rhyd Ddu.
This southerly view (16/2/03) shows rail laid on the site of Snowdon Ranger Halt (Ch.11400). There is sufficient rail here to complete the section over Glan-yr-afon Viaduct to meet up with the Head of Steel that was laid last year from Rhyd Ddu north. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The overflow channel deck at Tros-y-gol has been cast and all that is required is backfilling the abutments and cladding. Work was underway on 16/2/03 cleaning up the bridge girders and painting them.
This northerly view (26/1/03) shows the south bank of the Tros-y-gol bridge courtesy of a special site visit authorised by the WHLR and Jones Bros. The girders were being de-scaled by volunteer working party and then painted with special epoxy silver primer. The cross members will be cut out when Plas-y-nant bridge is finished. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
This southerly view (16/2/03) shows the north bank of the Tros-y-gol bridge with the south abutment and overflow span in the background courtesy of a special site visit authorised by the WHLR and Jones Bros. The overflow span was cast a few days previously. Good progress with this bridge may see it placed back on its abutments in March. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The water main just south of OB71 at Castell Cidwm has now been exposed. This will be excavated and buried deeper under the trackbed (presumably at the local Water Authority's expense!).
This southerly view (16/2/03) shows the excavation of the water main just south of OB71 at Castell Cidwm. When this is buried at a suitable depth, Jones Bros will complete the formation to meet with the completed trackbed from Snowdon Ranger finished last year by Brian Humphries. The summit of Snowdon is visible in the background (left of tree) with a light covering of snow. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Halting progress!
Progress with intermediate halts remains subject to finance outside that of the Millennium Commission project funding. There is hope that the Slate Valleys Initiative will fund the extension of a cycleway from Rhostryfan down to Tryfan Junction along the old trackbed. Tryfan Junction could then usefully serve as an interchange point for cyclists.
Halts have also been mentioned in the Nant-y-Betws valley, south of Waunfawr. While a halt for Bryn Gloch campsite would make economic sense for the railway and the campsite, the campsite owner is apparently opposed to this. There is no such problem at the Beddgelert Forest campsite, where another halt has been mooted for Phase 4, and there is a possibility of business transfer from Bryn Gloch as a result!
While Plas-y-nant Halt is on hold due to funding constraints, a correspondence in Snowdon Ranger reveals there are supporters for reviving Salem Halt. The future of this location may be considered after the route has opened to benefit the local community as was the case at Bontnewydd. The location of the platform would probably be immediately north of LC37 with access to Salem provided from the footbridge.
Progress to 10/2/03
Progress has been made with the abutments for UB56 at Tros-y-gol. The foundation slab for the north abutment was been cast by 6/2/03. This abutment has now been built up to its full height. The piers have also been cast for the south abutment. Thus structural concrete for both abutments is now complete. Work is now in progress on the shuttering for the south abutment flood relief span.
Timetable/fare changes
Rumours persist that the new timetable leaflets are to be replaced due to errors e.g. no departure time for Waunfawr in the Winter timetable. It is believed separate WHR and FR versions will be ordered to ensure both railways appear on tourist leaflet racks. There have also been suggestions that the 0850 peak diesel service will be dropped. The current version suggests that the Plas-y-nant extension will be opened on 14/4/03 and the Rhyd Ddu extension on 28/6/03 in time for the school Summer Holidays.
Fares for 2003 for the Day Return/Full Day Rover are £14 adults, £11.20 Concessions and £28 Family (2+2). A new Half Line Day Return/Day Rover is available at £8/£6.40/£16 respectively. The half line ticket applies to Caernarfon-Waunfawr or Waunfawr-Rhyd Ddu, anticipating persons who just wish to travel on the new section of line. One child under sixteen travels free with each adult. Other children travel at half fare. Children under 3 are free. There is a combined WHR/FR 3 days in 7 Ranger at £35/£28/£70.
Corporate News
WHLR Chairman Michael Whitehouse will become FR Chairman on 13/2/03. Last year was very successful with some 50,000 journeys being made, representing a quarter of the FR/WHR passenger business. Currently, Sundays are seeing regular coach bookings, justifying the 2003 venture to open throughout the year. The WHLR is to order additional coaches from Boston Lodge to cope with the anticipated traffic generated by opening to Rhyd Ddu but two FR corridor coaches are due to be transferred to Dinas for the anticipated increase in traffic.
The Welsh Highland Railway Society became a registered charity on 1/1/03. It is named Cymdeithas Rheilffordd Eryri to distinguish it from the long established '64 Co. charity but can trade using its English name.
Main Contract started 10/6/02
Roland Doyle (WHLR Manager) announced on 22/5/02 that Contract 3C has been let to Jones Brothers (Ruthin). This is not surprising as they are already on site at Cae Hywel and they have been able to offer a cheaper contract because they do not need to set up site offices etc. The official starting date is Monday 10/6/02, though some tasks such as boundary and site fencing may be done before then. The contract is worth approximately £1 million and must be complete by the end of the year as that is the cut-off point for the WHR Lottery Grant.
This northerly view (25/6/02) shows the trackbed just south of Cae Hywel bridge. The 10m surveyor's posts are now in position and rock is being removed from the Bryn Gloch cutting to extend the access road left. Click on the image to enlarge. This image is copyright WHR, courtesy Jan Woods. iPhoto Plus4 image correction technology and displayed at 96dpi.
Having a planned duration of 20 weeks, the expected contract completion date is 27th October 2002. There will be stage completions and handovers during this period to allow tracklaying to proceed (see below). The WHLR are now in the process of writing to adjacent landowners informing them of the start date, and plan to have an open evening before the Rhyd Ddu Earthworks commence. With the main Phase 3 contract signed, work will begin on the Cae Hywel to Castell Cidwm section, Glan-yr-afon viaduct, and Rhyd Ddu station deviation. Work is already underway by WHLR employees and subcontractors on the section between Castell Cidwm and Snowdon Ranger and they will turn their attention to the Snowdon Ranger to Glan-yr-afon section in the Autumn after completing the section north of Snowdon Ranger.
Jones Bros. will complete the stretch from Betws Road bridge back to UB56 by end of June and hand it over as a ballasted trackbed. By that time the tracklaying volunteers should have reached Glan-yr-afon and will probably switch to laying track north from Cae Hywel (Ch.7900) for 850m (about 50 lengths). Cae Hywel could be the tracklaying base camp. Tracklaying will proceed north toward Betws Garmon and under the main road bridge (OB53), which GCC should have completed by then, to Ch.7050 just short of the Afon Gwyrfai bridge (UB51).
This southerly view (3/6/02) from Ch.8200 near Salem shows the pristine trackbed days before work was due to begin. The beautiful curves along the banks of the Afon Gwyrfai still show their sleeper marks from when the track was lifted 60 years ago. Click on the image to enlarge. This image is copyright WHLR, courtesy Jan Woods with post processing using iPhoto Plus4. Image displayed at 96dpi.
This southerly view (25/7/02) shows progress at the same location as seen in the previous illustration. The trackbed has now been fully consolidated and is used as an access road to locations further south. Click on the image to enlarge. This image is copyright WHLR, courtesy Jan Woods. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The short section north of OB53 will be completed and ballasted by the WHLR as soon as GCC clears the site, hopefully in June. This gives the possibility of tracklaying working south from UB52 if Jones is unable to accommodate the rail stack at Cae Hywel.
During the period June to August the appointed contractor will be working south from Cae Hywel (Ch.7900), including the refurbishment of the Afon Gwyrfai bridge (UB56). By mid-August it is hoped that the contractor will hand over the ballasted trackbed to about Ch.8750 and, in this case, the tracklaying volunteers can then progress south from Cae Hywel for 850m (about 50 lengths).
For the work south of UB61, contractors will work from a site at Plas-y-nant. This site was established by 5/7/02 between the railway and the main road just south of UB61. They will also refurbish the final Afon Gwyrfai bridge (UB64) at Plas-y-nant. The works include the widening of the formation for the passing loop south of Plas-y-nant Halt and completion of the trackbed to Castell Cidwm at Ch.10100.
Towards the end of Summer/early Autumn the trackbed available for tracklaying should extend further on to Castell Cidwm. Meanwhile the WHLR should have the trackbed south from Castell Cidwm to Snowdon Ranger finished by late Summer so the tracklaying volunteers can switch to this length if they complete the section south from Cae Hywel to Pont Cerrig-y-rhyd before the contractors have finished to Castell Cidwm.
Contracts latest
The WHLR awarded the final contracts (see above) on 22/5/02 and work should be underway by 10/6/02 on the central section through Salem, from Cae Hywel to Castell Cidwm. The aim is to complete the railway to Rhyd Ddu by Xmas, which should permit the public opening next Easter, once the track is tamped and HMRI approval has been received. The 1 month delay was primarily caused by the F&M epidemic.
The Cae Hywel bridge (UB56) will see the abutments rebuilt and wrought ironwork reused with new timber waybeams provided. Currently, 20 tonne dumpers have been driving over this bridge carrying spoil surplus from OB54 excavation to build the new Cae Hywel access track. To facilitate this spoil shift, the beam ends have been temporarily propped in front of the existing abutments. The Plas-y-nant bridge (UB64), will see the wrought iron transom beams (cross beams) replaced by larger steel ones. New waybeams will be provided.
The WHLR is aiming to place contract 3C by the end of May. It includes the Rhyd Ddu station site where trial pits have revealed that there is much less rock than at first anticipated and that the majority of the non rock material is of a reusable nature.
Coupled with the WHLR's direct labour gang commencing work on contract 3E1 (Castell Cidwm to Glan-yr-afon) in the next few weeks, by the end of May all contracts will be in place except the deck of UB51 (Afon Gwyrfai Bridge at Betws Garmon) to complete the formation to Rhyd Ddu.
The WHLR team will start on the fenced section from Castell Cidwm to Snowdon Ranger. The section from Snowdon Ranger to Glan-yr-afon viaduct will be tackled later. This section needs fencing and tree felling which cannot be started until the end of the bird nesting season in June.
Tracklaying at Salem
Tracklaying was underway at Salem w/e 1/12/02. Some six lengths were laid through the curves, terminating midway between LC35/36 at Ch.8330 approx. Tracklaying has reached the end of the sharply curved section and will proceed along the relatively straight section towards Salem Halt (opposite the footbridge). It is hoped that the section to Plas-y-nant will be finished by the New Year following a 5 day trackbash over Xmas given reasonable weather.
Six more lengths were laid south from LC36 over the weekend of 14-15/12/02.
24 more lengths were laid over the 5-day Xmas working party in rain and bitter weather. Work should be complete to Plas-y-nant bridge by the end of January given good weather.
This northerly view (31/12/02) shows the Head of Steel at Ch.8763 entering the long straight along the rock shelf at the end of the final day of the 5-day Xmas working party, which beat the target of the level crossing in the background. The skip is being used to ballast the formation through the level crossing. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Tamper Appeal
Welcome news to the PW gangs is that the Matisa A05 tamper was delivered to Glan-y-pwll depot from Crewe in January 2002. This originally metre gauged design was re
-gauged to standard gauge for use on the Jubilee Line project by GTRM. Following the completion of that project, agreement was reached to purchase it for the FR/WHLR last October.The tamper will fit the WHR loading gauge but at a later stage will be cut down to fit the FR as well. It has adjustable banks to work over pointwork. Sleeper spacing is also different under the rail ends where closer sleepers provide extra support around the fishplate.
WHLR staff were delighted that it started first time after over a year out of use and that the hydraulics all seemed in order. The unit will probably be delivered to the WHR as soon as possible to tamp the existing running line and improve the already laid extension to Betws Garmon, which is currently prohibited to locos.
The wheelsets were taken to the Talyllyn Railway's Pendre works but their hydraulic press was at first unable to remove the wheels from their over gauge axles despite the 250 tons pressure. The wheels were later removed.
An appeal has been launched for funds to purchase the tamper. A deposit has been paid but £55,000 must still be raised (or about £25 per WHRS member!). During April the fund reached around £10,000. There is also hope of raising funds for another piece of vital on-track plant. For latest news see above.
If you can help please send a cheque made out to 'FR Trust WHR Account' to the Fund Organiser Mark Neilson, 8, The Furrells, Linton, CAMBRIDGE CB1 6JJ. For further details telephone 01223 894058 or email mailto:mark1cwneilson@tiscali.co.uk
Pont Cerrig-y-rhyd (OB62) to Salem
Work started on the 1m deepening under Pont Cerrig-y-rhyd in July. The initial cut followed replacement of fallen masonry and pointing with an untypical grey mortar on the railway faces. On 6/8/02 Jones did the basic trackbed excavation both north and south of the bridge. A specialist subcontractor was called in to do the delicate rock pecking around the foundations. Concrete bracing supports have been constructed for each abutment.
This northerly view (26/8/02) shows the completed underpinning of OB62 at Pont Cerrig-y-rhyd. This has been a much smaller job than anticipated as the rock under the foundations was mostly sound. Click on the image to enlarge. This image is copyright B.W.Hughes. Image taken on Samsung Digimax 230 digital camera using iPhoto Plus4 image correction technology and displayed at 96dpi.
The trackbed is being lowered by about 1 metre under Pont Cerrig-y-rhyd (OB62) by excavation of the rock cutting and underpinning the abutments to achieve the standard 3.660m clearance required by the modern loading gauge. This will cause the gradient to be eased to 1 in 200 north of the bridge followed by an increase to 1 in 60 south of the bridge. The previous trackbed levels will be regained by the Afon Gwyrfai bridge at Plas-y-nant (UB64). However this does mean that the rock wall embankment through the picturesque Gwyrfai Gorge at Nant Mill will be reduced in height a little.
Work was also underway at the south end of the embankment at Nant Mill by 24/8/02 where the river has scoured out a small area of the stonework. The river was sandbagged away from the location and concrete infill is likely with local stone facing. This work was extended to new areas along the rock wall by 26/9/02.
This southerly view (14/9/02) shows the completed trackbed from OB62 at Pont Cerrig-y-rhyd. Drainage remains to be completed. Click on the image to enlarge. This image is copyright B.W.Hughes. Image taken on Samsung Digimax 230 digital camera using iPhoto Plus4 image correction technology and displayed at 96dpi.
By 26/9/02, ballast was also being laid north from Pont Cerrig-y-rhyd Ch.8880 towards Cae Hywel as far as Ch.8800.
This southerly view (26/9/02) shows the completed ballasting of the formation and placement of steel sleepers at Ch 8800 on the rock wall near Salem. Click on the image to enlarge. This image is copyright WHLR, courtesy Jan Woods. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
Track Gap countdown!
(This feature has been replaced by a tracklaying progress table on the main Stop Press page)
On 10/8/02, tracklaying commenced from Cae Hywel towards Betws Garmon. Work started at Ch.7860 and by the end of the weekend was completed to Ch.7644, a distance of 216m (12 lengths). Two temporary lengths are also laid in the rail store at Cae Hywel. Some 614m of ballast is available to lay track on from Ch.7245 (Bryn Gloch) to Ch.7860 (Cae Hywel).
Some additional tracklaying took place by 16/8/02 almost reaching the new position of LC31 behind the waterworks at Ch. 7540 approx. The 'top' on this section is a little uneven as Jones Bros. apparently did not roll the ballast to consolidate it. Subsequent top ballast and the attention of the new tamper will provide a top speed of 25mph eventually on this 500m+ straight.
Four more lengths of track were laid on 24-5/8/02 reaching Ch.7466, some 394m in all. This includes a small dogleg by the new LC31. The track is now visible from OB54. Additional lengths were laid on 7-8/9/02 with the Head of Steel approaching OB54 at Ch. 7240 by 14/9/02. Work was complete on this section by 22/9/02 and further work was hampered by flooding under OB54. There are some 620m laid in this section.
It is unclear when tracklaying will start on the section north of Snowdon Ranger (ballasted and some sleepers laid ready) as this is the only section without a rail pile! Jones Bros. handed over the section from Plas-y-nant (exclusive) to Tros-y-gol in early November and work started from the north end at Tros-y-gol where a small supply of rails was craned over. Full access can only be made from Plas-y-nant rail pile once the bridgeworks are complete at Plas-y-nant.
Nevertheless the tracklaying volunteers have been preparing points at Dinas (29/10/02) and laying sleepers in preparation on the trackbed. John Sreeves laid sleepers on the section north from Snowdon Ranger (Ch. 11120 to Ch.11250) in early October. Over the weekend of 2-3/11/02, the tracklaying gang laid the sleepers from Plas-y-nant north (Ch.9060) towards Salem, through Pont Cerrig-y-rhyd, reaching Ch.8300 by the end of the weekend.
Rail was actually craned over at Tros-y-gol w/e 17/11/02 from the Dinas stockpile. Two temporary lengths were laid just south of the stockpile and, over the weekend, six permanent lengths (108m) were laid terminating adjacent to Tros-y-gol Ch.8130 approx. The rail store is sufficiently far from the abutment of UB56 to allow its rebuilding without interference. The rail used has previously been used on curves in South Africa and this will help as this section is sharply curved.
It is stored in two stockpiles, namely left curves and right curves (as laid down on the trackbed). As the temporary siding has to be clear of the Tros-y-gol access, a Landrover is used to winch the rails to the start of the temporary track at Ch 8065.
This northerly view (30/10/02) from Bryn Gloch bridge shows the completed track on this section. After heavy rain, the cutting has collected water and needs a drain to the north end through OB53. Ballasting and tracklaying to UB51 will have to await this work. Click on the image to enlarge. This image is copyright B W Hughes taken on Samsung Digimax 230 digital camera. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The rail head at Betws Garmon station is now at Ch.6919 and the cut-back termination of Phase 3 is at Ch.14875. Add in the 200m loop at Rhyd Ddu and a similar 300m loop at Plas-y-nant and altogether some 9500m of track must be laid. Well over 1 mile of track has been laid since the start of work on 27/10/01 with 1579m laid from Ch. 14495 to Ch.12916 by the end of June 2002 from Rhyd Ddu to Glan-yr-afon.
Jones Bros. reschedules contract for January finish
Accepting the difficulty of working through the winter and the state of current progress, Jones Bros. has estimated that it may take until the end of January to finish their works. This ties in well with the contingency plans the WHLR has developed (see below). Jones Bros. handed over the completed and ballasted section between Plas-y-nant (exclusive) and Tros-y-gol in November but completion of tracklaying to Plas-y-nant will necessarily await the completion of UB64 (see below).
Work is soon to start on the Glan-yr-afon viaduct. Agreement has been reached to place reinforcing plates on the middle of every other of the large plates that form the main girders rather than replace all the splicing plates as originally suggested. The additional plates are currently being manufactured.
Ballasting through Salem
Jones Bros. made good progress ballasting north from UB64 w/e 3/11/02. Work reached Ch.8300 between LC35/36 by 1/11/02 despite the wet weather. The intention was to complete ballasting to Tros-y-gol by early November at about 60m a day.
The isolated section north of UB64 and south of OB62 (Pont Cerrig-y-rhyd) was ballasted through OB62 and joined up with the previous section on the rock wall at Ch.8880 during October. A step in the ballast bed under OB62 is designed for wooden sleepers as it will require a check rail.
This northerly view (30/11/02) from OB62 shows the recently completed trackbed at Pont Cerrig-y-rhyd. A van is seen using the newly diverted road access to the house. The step in the trackbed shows where wooden sleepers will be used to allow check rails to be fitted through the bridge. Click on the image to enlarge. This image is copyright B W Hughes taken on a Hitachi D8 digital camcorder VM-D865LE 230. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The ballast bed reached LC34 (Ch.8100 approx.) by 9/11/02 and preparations were made for lifting some rail over the Afon Gwyrfai from Cae Hywel so that tracklaying may proceed south along the newly ballasted section. A crane was on site at UB56 at Cae Hywel later in the week, shared between the WHLR Ltd. and Jones Bros.
During the first half of hire the WHLR Ltd. received a couple loads rail that were craned over the bridge to make a rail stack for laying southward. So rail is now in place for volunteer track laying to get back underway from 16/11/02 over the 1100m from Ch.7950 to Ch. 9050 approx. This section will require some 62 pairs of rail. Jones then used the crane to lift the complete assembled bridge span out and place it on dry land at Cae Hywel for refurbishment. It was felt that, with shared crane costs, it was economic to remove the span and so make the rebuild of the abutments easier.
UB64 progress Plas-y-nant
Jones Bros. made good progress on UB64 at Plas-y-nant w/e 3/11/02. It has been decided to make the southern abutment and overflow channel in reinforced concrete with local stone cladding. By the end of the week, the contractors had made formwork for a reinforced concrete slab approximately 6m long by 5 metres wide by 1m deep to lie under the overflow channel. This will support the piers for the main span and the land abutment at the south side.
The casting of the base slab was completed w/e 10/11/02 but work came to a stand again as the site was flooded with water over the slab. It was impossible to make any progress on the central pier or the southern landward abutment.
However, as soon as the floods abated, Jones Bros cast the central pier and the land abutment, which were completed by 17/11/02. These will be clad in local stone after the Winter floods.
By w/e 24/11/02, the shuttering and steel reinforcement was complete for the overflow channel span. The shuttering for the capping slab on the north abutment was also in place and the reinforcement was complete there too. It seems both of these will be cast from the same delivery of cement during the last week of November.
By w/e 1/12/02, the deck of the overflow channel span had been cast and formwork for upstands were being constructed for ballast retention. The northern abutment was also receiving upstands to retain the girders.
This westerly view (30/11/02) of UB64 shows the cast re-inforced upstands on the completed overflow channel deck. These were cast the previous day and retain ballast from falling over the sides and bridge girder end. It seems the whole bridge has been raised by 0.4m. Click on the image to enlarge. This image is copyright B W Hughes taken on a Hitachi D8 digital camcorder VM-D865LE 230. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
The transverse beams between the two main girders will be replaced by new beams presumably manufactured by local steel company Brunswick Ironworks. The bearings will be refurbished and re-instated.
By 7/9/02, the north abutment of UB64 at Plas-y-nant had been sandbagged to allow excavation of the undermined area. This will probably be rebuilt with reinforced concrete with a local stone facia. The bridge itself is now resting on props. There is some question about the gravel foundations. There was no progress by 14/9/02.
However, by 21/9/02, the corner had a foundation cast in situ and by 26/9/02 the corner had been reconstructed in local stone facing. By w/e 13/10/02 the pier at the south end was sandbagged off and work was underway on both the pier and the southern abutment. The space between is an overflow channel.
By 20/10/02 the work on the southern overflow channel pier and abutment had seen their removal. these will be replaced by new structures with local stone facing. The northern abutment was complete and back filled and ballast laid from a point about 4m north of the bridge Ch.9060 approx. to Ch.8930 approx, just short of OB62 (Pont Cerrig-y-rhyd).
Work on the southern abutment and the flood channel pier, which supports the south end of the bridge span, had previously come to a halt w/e 27/10/02 with no apparent progress. This was because the works had become flooded, the river having overtopped the sandbag wall. Pumps are on hand to clear the works.
A ballast pile has been established on the trackbed immediately south of LC41 at Plas-y-nant. The westerly track has been ballasted from LC42 for about 60m north. This leaves room for the plant road for the 500m length south of the loop.
This southerly view (26/9/02) shows the completed north abutment of the Afon Gwyrfai bridge at Plas-y-nant. The abutment has been reconstructed using local stone facing. The bridge is still propped and no work appears to have been done on the deck yet. Click on the image to enlarge. This image is copyright WHLR, courtesy Jan Woods. Image post processed using iPhoto Plus4 image correction technology and displayed at 96dpi.
By 17/7/02 the trackbed had been scraped through the Gwyrfai Gorge to Pont Cerrig-y-rhyd. There is a WW2 blockhouse just north of the bridge, above the railway. Moves were underway to prop the bridge by 8/8/02 and the mortar launcher base was removed the same day. By mid-August the bridge was propped though no further progress was visible by 26/8/02 (but see above).
Funding sought for Rhyd Ddu-Beddgelert cycle path
At a recent meeting
in Autumn 2002 (one of a series) between representatives of the WHLR and the Snowdonia National Park Authority's Welsh Highland Railway Panel, it was announced that funding was to be sought for a feasibility study into a cycleway alongside the line between Rhyd Ddu and Beddgelert (Phase 4). The feasibility study would depend on the availability of grant monies. Considerable use could made of the cycle path as Beddgelert Forest is a well known biking centre and much of the trackbed between Pont Cae'r Gors and LC82 (Afon Cwmcloch bridleway) is currently used for the same purpose.The main road between these two locations is narrow and steep and unsuitable for walkers (no footpath) or cyclists weaving because of the steep gradient. If built, the footpath/cycleway would probably mimic the Lon Eifion alongside the Caernarfon to Dinas section and provide a wealth of locations where the locomotives can be observed working hard up the 1 in 40 of the Nant Colwyn Pass, north from Beddgelert.
The route would probably lie between the railway and the main road